Munro Road Resilience and Footpath design
Project objective
Upgrading the culverts beneath Munro Road, raising the road and installing a pedestrian path. Flood prevention and resilience project.Project update
June 2026 - Design nearing completion including triple 2m diameter culverts and cast insitu concrete aprons. Coordination with Counties Energy has resulted in a design that is approved by Counties Energy for clearances in and around the buried power cables and overhead lines."For Tender" documents will be available for contractor pricing on 1 July 2026.
At a glance
Status
Active
Categories
Roading
General wards
Tuakau-PÅkeno General Ward
Maaori wards
Tai Raro Takiwaa Maaori Ward
Towns
Pookeno
Completion date
April 2027