Munro Road resilience and footpath

Our focus will be on upgrading the culvert beneath Munro Road and raising the road to enhance its resilience against potential floods.

This project is a significant step towards creating a more flood-resistant environment for everyone. 

Project Update

June 2024 - The start date for Munro Road has been pushed back to September 2024.  The resource consent enabling stream does not allow for works July to September due to fish migrations.

At a glance
Status
Active
Categories
Roading
Maaori wards
Tai Raro Takiwaa
General wards
Tuakau-Pōkeno
Towns
Pookeno
Completion date
December 2024 - January 2025