Ngaaruawaahia Dog Pound
New Build of Dog Pound. Dependent on feasibility study to decide between separate buildings or centralised. # Figures require QS. FY24/25 renewals to also be completed as part of the building upgrade.
Project Update
June 2025 - The relocation of the fencing including the acoustic has been completed. Building 1 has been emptied with demolition work planned to commence the week of the 09 June. The Admin transportable building has passed structural and pre-line inspections, ready for roofing and cladding.
At a glance
Status
Active
Categories
Public facilities
Maaori wards
Tai Raro Takiwaa
General wards
Tuakau-PÅkeno
Towns
Tuakau
Completion date
October 2025