Onewhero Domain Lighting Upgrade
Lighting upgrade for the Onewhero Domain
Project Update
June 2025
- The lighting poles and the fixtures are now installed.
- All of the cables from the poles are now connected to the control board.
- The top 200mm of the old pole foundations were removed with re-instating of topsoil and grass seed.
Upcoming
- Installation of the main switch board with a 63A outlet.
- Commissioning of the power connection to the main switch board
- Lighting survey (to ensure we meet the design intentions)
- Blessing ceremony and celebration to mark the completion of the project.
At a glance
Status
Active
Categories
Parks and reserves
Maaori wards
Tai Raro Takiwaa
General wards
Western Districts
Towns
Onewhero
Completion date
August 2025