Pookeno Sports Park
Project objective
Pookeno Sports Park (Te Kupenga Wairepo o Pookeno) is designed to be a place that connects us and celebrates nature, recreation, and community.
With the Master Plan complete, we’re moving on to the next stage of the concept design of the playground and skatepark.
Background
This project has been a community priority since 2014. Over the years, Council have worked closely with the Pookeno Community Committee (PCC), mana whenua, and Sport Waikato.
- Public steering - Previous engagement over the years has seen over 300 community submissions, which helped directly informe the creation of the park's Master Plan.
- Master Plan creation: Pookeno Sports Park Masterplan was completed in August 2025, providing the blueprint for the future of the park.
- Concept designs for playground and skatepark.
- On-site progress: Extensive civil works has already been completed, including stream diversion, site levelling, and the completion of a 70-space car park.
Project update
We have reached an exciting milestone! We are moving from the high-level Master Plan into the concept design phase for our two biggest features of the park: the destination playground and the skate park.
Since the community has already provided a steer on the overall layout of the park, we the sought specific feedback on the look and feel, and specific elements of these zones to ensure they meet the community’s needs.
- Destination Playground: Resource consent has been granted. Aiming for enabling work for site services (water and wastewater) to start late 2026. Physical works for playground will commence mid-January 2027. With the aim to be completed in late May 2027.
- Skatepark (The ‘Youth Zone’): This area is intended to be a vibrant, safe congregation area. Construction is planned to start mid-January 2027 and completion late May 2027.
- Public toilet – Enabling works for services have started, with the aim to complete the toilets in February 2027.
- Pedestrian bridge connecting Waikaha Street to the sports park: Detailed design is complete and bridge fabrication is underway. The main bridge structure installation will happen early 2027.
Last updated: November 2026
Timeline
-
February 2026Early community input on design, engagement with mana whenua and field improvements
-
March / April 2026Draft concept designs presented and fundraising for the skatepark
-
May / June 2026Final detailed design completed
-
Decemeber 2026 / January 2027Construction planned to start for playground and public toilet
-
2027Playground and public toilet open to the community